Can products be changed after Gateway 2? Yes. Individual products on a project can be changed after gateway 2. All changes do have to be submitted to the Building Safety Regulator (BSR) and there is secondary legislation coming on this. However, it’s thought there’ll be 2 categories. The first will be major changes that will have a six week period for the building safety regulator to review that change and come back with a yes or no answer. However, if the Building Safety Regulator does not come back with a response within six weeks, it’s deemed as a default no. The other type of change is what they call a notifiable change. Now the BSR has ten days to review and if they do not respond within the ten days, it’s deemed as an automatic yes.